Delivered
26 substations with complete equipment, connecting and commissioning.
20 kV cable and telecommunications line along the entire length of the route of 41 km. Cable lines were installed both on the open highway route and through 16 tunnels with a total length of 17.74 km and under 20 bridges with a total length of 6.1 km.
Year
2022
The project included the construction of 20/0.4Kv substations with 20kV cable distribution and a remote control system for powering buildings along the entire route of the Bar – Boljare highway, Smokovac – Mateševo section. The construction of the 41 km long section took seven years, and the work was completed in mid-2022. The implementation of this project will improve the transport network in Montenegro, but also valorize the economic potential of all gravitating areas.